Leaders
in Malava constituency have been accused of engaging in bribery demands to
award road tenders to contractors whom in turn have done shoddy work on the
allocated routes.
The
alleged leaders, from the area MP Malulu Injendi, to reps are said to be on the
forefront in demanding kickbacks and awarding verbal contracts to the
contractors who use their own money to carry out the works and only end up not
being paid upon completion of the work.
The
revelations have emerged after roads within the constituency that were graveled
became impassable forcing boda boda operators to demonstrate.
Investigations
reveal that there is a clique of operatives who are working in cahoots with the
ward representatives and even the area MP that is said to be demanding bribes
before the tenders can be awarded to the contractors.
A
case in point is Musungu to Lusumu bridge road which was verbally awarded to a
contractor John Marani but after completion of the works, the procurement office was unable to pay him
as he did not follow due process of tendering as required by law.
It
is alleged that the contractor had spent close to Sh1 million that he can only
be paid in the next disbursement of funds.
Marani
who is now a bitter man had allegedly been awarded the contract by
Mugai/Shirugu MCA Albert Wetundu. Asked why he was awarded the contract
verbally, the contractor said county representatives were money hungry and had
received bribes even from roads that were not earmarked by the county
government but he was hesitant to divulge if he had also paid any bribe to
Wetundu.
But
sources close to MCAs disclose that many contractors are on their necks
demanding either contracts or a refund of their bribes and therefore end up
being awarded ghost contracts.
Marani
has also accused area MP of awarding tenders without even advertising, a case
in point being the Malava-Lugusi road which is 2.7 kilometres and is incomplete
even after spending Sh4.4 million on it. The contract in question was awarded
to a one Steve Malumasi through his Silwa Construction Company and of which the
MP who hails from the same area is alleged to be also demanding for kickbacks,
according to Marani.
Other
roads which have been cited in the scandal and are all found in East Kabras
ward include Kakoyi- Mukhuyu, which is said to have cost Sh1.2 million, Bunuku
Bridge to Bunuku Primary at Sh600,000, Shianda to Forest at Sh 2 million with a
resident Machoni Chiteyi accusing the area MCA Peter Mwombe of employing
unqualified contractors whom he alleges cough bribes to him yet end up doing
shoddy jobs.
Asked
to specify the amount given to the MCA, he denied knowing the exact amount but
maintained that it is in hundreds of thousands.
Reached
for comment, the area MCA denied the bribery allegations and instead said if
there’s any corruption, it should be at
the procurement office and not him and went ahead to state that Chiteyi who is
accusing him was among those employed to supervise the repairs on the said
roads and should therefore be responsible for the shoddy works, a claim Chiteyi
also denies.
Kenya
Rural Roads Authority officer a Ms Jerusha who is in charge of tendering
accuses Silwa Construction Company of doing a shoddy job on all its roads
allocated to them and wondered why it is Silwa alone that is being awarded.
She
revealed that all the construction companies that have so far been awarded have
proved to be incompetent and may not be awarded any contract in the near
future.
She
said that some companies have neither done the road works and even others are
yet to start working, blaming their delay on the ongoing heavy rains pounding
the area while others take too long than the required period.
According
to the local chairman of Kerra Moses Wasike, Sh15 million was allocated for the
roads in Malava constituency in the last financial year 2013/14 while this
year, a total of Sh13.9 million has been allocated.
Wasike
agreed that the roadworks was a major setback to development within the
constituency and blamed most contractors to failing to meet the required repair
standards and instead turning most roads into a muddy path that was impassable.
Last
week, residents of Kakamega North district in Malava constituency of Kakamega
county took to the streets protesting over what they termed as bad state of the
roads within the area.
The
demonstrations led by the boda boda chairman Bernard Munanga and an activist
Joshua Masitsa accused the leadership of the area led by MP, the MCA under the
auspices of Albert Wetundu for failing to ensure that the contractors did a
perfect job.
They
alleged that contractors awarded tenders were not genuine and had bribed their
way into being awarded the same and promised they will vote out all the leaders
involved in the scandal.
Masitsa
was categorical that both Malava MP and Mugai/Shirugu ward representative were
demanding huge perks from would- be contractors before awarding them with the
tenders.
They
attributed the poor state of the poor works done to the huge perks paid to the
leaders, hence softening there supervision on the contractors.
The
MP and his Mugai/Shirugu MCA have distanced themselves from the corruption
allegations and stated that the awarding of the tenders was in tandem with the
procurement procedures and instead called on the contractors to carry their own
cross if they were unable to deliver.
At
the same time, sources within the Malava CDF office reveal that the MP single
sourced the contractor and the tender committee might have only worked on an
order from him.
It
is further alleged that the MP is trying to negotiate with a contractor whom he
is said to have sold a plot to fund his campaigns in 2017 elections and now
wants to repossess it as it is in a prime area within Malava town as he is
alleged to have promised a contract in return.
It
is the county government of Kakamega and Kenya Rural Roads Authority that are
funding the gravelling of the sub-county roads. In Malava constituency, Kerra
is expected to gravel 13 roads.
Chimuche
ward MCA Steven Ambulwa expects Sh56 million for the gravelling which he
anticipates the county government will allocate soon.
His
South Kabras ward counterpart Bryson Sikolia says he needs Sh30 million more
from the Sh5 million to complete the projects.
So
far, he has done murraming Chevoso to Musali junction road and West Kenya to
Catholic Lubao road at Sh2.2 million and Sh2.3 million.
Sikolia
maintains that whether leaders demand bribes from contractors or not, what is
needed is efficient service delivery of the tender awarded and warns that in
his ward, he has no room for unqualified contractors.
As
much as Malava constituency is concerned, we established has received over Sh50
million for roads improvement. It is
only South Kabras, Butali Chegulo and Chimuche wards that the public audits
approve of having done a good work.
No comments:
Post a Comment